Market Note
Connection, not capital, is the bottleneck in the National Electricity Market


27.11.2026
/
Posted by
Chief Financial Officer
Market Note
In our view, capital is not what limits new generation in the National Electricity Market. Projects that are approved and connectable are scarce. That is why Saltbush is built around approvals and connection.

The connection queue
Under NER Chapter 5, a new generator applies to the network service provider, completes studies and agrees network works before it connects. In South Australia that is ElectraNet for transmission and SA Power Networks for distribution; in Victoria, AusNet Services and Powercor.
AEMO then has to accept the generator performance standards and the models behind them. Each step takes time, and many projects wait for the same studies and the same network capacity, so connection timelines are hard to compress.
Thermal retirement in SA
South Australia is retiring thermal plant, which raises the need for new supply and for system strength. It also means connection points and the network near them are contested. Projects with an executed connection agreement and accepted standards are ahead of those without.
Why approvals are not enough
A planning approval does not deliver connection. A project with approval but no connection path cannot reach financial close, and one with network access but no approval cannot be built. We aim to hold both, and run Gate 4 and Gate 5 work in parallel from Gate 2.
What we do about it
We start connection enquiries at Gate 2, rank sites on network evidence before spending on approvals, and require Investment Committee sign-off at each gate. We cannot shorten the NEM queue; we can decide which projects deserve a place in it.
Explore More

18.12.2026
Posted by
Saltbush Renewables
Saltbush plans to hire 45 people across engineering, approvals and delivery in 2027
Announcement

15.12.2026
Posted by
Saltbush Renewables
Saltbush sets out a five-project, 1,510 MW opening pipeline
Announcement

10.12.2026
Posted by
Chief Financial Officer
Why midday prices in South Australia make storage a design condition
Market Note

04.12.2026
Posted by
Saltbush Renewables
Saltbush plans a Horsham field office for its western Victorian projects
Announcement

01.12.2026
Posted by
Chief Development Officer
Why we sign native title and heritage agreements before we fix the layout
Technical Note

24.11.2026
Posted by
Chief Development Officer
How we test a site for connection before we pay for approvals
Technical Note

21.11.2026
Posted by
Saltbush Renewables
Saltbush Renewables is established in Adelaide
Announcement