Why we sign native title and heritage agreements before we fix the layout

01.12.2026

/

Posted by

Chief Development Officer

Technical Note

We plan to sign native title and Aboriginal heritage agreements before we fix a project layout. Turbine, array and track positions depend on where heritage is, so the agreements come first and the layout follows.

Why the order matters

A layout drawn first has to be redrawn when a survey finds sites, objects or places of significance. By then land options, connection studies and approval documents may rest on the wrong footprint. Doing heritage first protects the approvals timeline.

Heritage surveys are run with Traditional Owner representatives, on their terms and timing. Their findings go into the constraint register that feeds the concept layout at Gate 2 and the final layout before Gate 4.

Avoidance first

Our rule is to avoid heritage by moving infrastructure. In South Australia, the Aboriginal Heritage Act 1988 allows an authorisation under section 23 to disturb sites, and we would seek one only where avoidance fails. In Victoria, a Cultural Heritage Management Plan is prepared with the Registered Aboriginal Party.

Native title and ILUAs

Where native title may exist, the Native Title Act 1993 provides for Indigenous Land Use Agreements (ILUAs). We take advice on the native title position of each site early and aim to have agreements in place with the right parties. Agreements are negotiated, so we do not forecast their terms or timing.

The Gate 4 test

Gate 4 evidence includes planning approval with a conditions register, heritage agreements and a native vegetation decision. Heritage agreements must be in place before a project exits Gate 4. A project without them does not advance, however good the wind or solar resource is.